At Northwick Clinics, a project manager is leading a hybrid records migration. During a steering committee meeting, the sponsor makes a sharp remark criticizing the project manager's competence. The project manager feels immediate anger.

What should the project manager do first?

  1. Escalate the sponsor's behavior to the clinic's human resources department immediately.
  2. Document the insult in the issue log and continue with the meeting agenda.
  3. Immediately correct the sponsor to maintain authority in front of the committee.
  4. Pause to regain composure and schedule a private meeting with the sponsor later.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials