Nimbus Clinics is transitioning to a hybrid delivery model for its new patient portal. A clinic manager acknowledges the project is necessary for long-term growth but refuses to participate in the pilot, citing that the new interface adds three minutes to every patient intake.

What should the project manager do first?

  1. Schedule a mandatory training session for the clinic staff to demonstrate the portal's efficiency.
  2. Conduct a private meeting with the clinic manager to identify the root cause of the resistance.
  3. Submit a change request to the CCB to simplify the interface requirements immediately.
  4. Escalate the manager's non-compliance to the Chief Medical Officer to ensure project adherence.

Sign up free to see the explanation and track your rank →

More Project Management Professional Hybrid Approaches practice

All Hybrid Approaches questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards