The project manager for Harborline Transit is preparing for a phase gate review. A key stakeholder is concerned that the project is delivering the 'wrong' features for the new ticketing system, despite the project being on schedule and budget.
What should the project manager do first?
- Review the business case and the requirements traceability matrix (RTM) with the stakeholder.
- Show the stakeholder the S-curve to prove that the project is performing at a CPI of 1.02.
- Inform the stakeholder that the scope was signed off six months ago and cannot be changed.
- Escalate the stakeholder’s dissatisfaction to the steering committee immediately.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?