medium · Project Management Professional hybrid

The project manager for Harborline Transit is preparing for a phase gate review. A key stakeholder is concerned that the project is delivering the 'wrong' features for the new ticketing system, despite the project being on schedule and budget.

What should the project manager do first?

  1. Review the business case and the requirements traceability matrix (RTM) with the stakeholder.
  2. Show the stakeholder the S-curve to prove that the project is performing at a CPI of 1.02.
  3. Inform the stakeholder that the scope was signed off six months ago and cannot be changed.
  4. Escalate the stakeholder’s dissatisfaction to the steering committee immediately.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials