An SME at Marrowfield Labs refuses to participate in knowledge transfer sessions, claiming they are too busy with the predictive workstream. The project manager notices this is affecting the adaptive team's velocity.

What should the project manager do first?

  1. Meet privately with the SME to understand their concerns and the value of their time.
  2. Submit a change request to extend the schedule to allow more time for the SME.
  3. Notify the SME's functional manager about their lack of cooperation.
  4. Reassign the SME's knowledge transfer tasks to a junior researcher who is more available.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials