An SME at Marrowfield Labs refuses to participate in knowledge transfer sessions, claiming they are too busy with the predictive workstream. The project manager notices this is affecting the adaptive team's velocity.
What should the project manager do first?
- Meet privately with the SME to understand their concerns and the value of their time.
- Submit a change request to extend the schedule to allow more time for the SME.
- Notify the SME's functional manager about their lack of cooperation.
- Reassign the SME's knowledge transfer tasks to a junior researcher who is more available.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?