hard · Project Management Professional hybrid

The Nimbus Clinics laboratory expansion is a hybrid project. The architectural work (predictive) is at the 'Identify Risks' stage. The software team (adaptive) is currently in a retrospective. A team member from the software team identifies a risk that the lab's new automation protocol might not be compatible with the legacy database.

What should the project manager do first?

  1. Ask the software team to add a 'Spike' story to the current sprint to investigate the compatibility.
  2. Record the risk in the project risk register and assign an owner to perform a qualitative analysis.
  3. Tell the team member to bring the risk up at the next architectural phase gate review.
  4. Submit a change request to the CCB to change the database architecture immediately.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials