KomFi. Academy

easy · Project Management Professional Hybrid Approaches

A senior developer at Nimbus Clinics is upset because their idea for a spike was rejected by the group in favor of another. They are now being very quiet in meetings.

What should the project manager do first?

  1. Publicly praise the developer's idea in the next meeting to make them feel better.
  2. Meet with the developer privately to acknowledge their contribution and understand their feelings about the group's decision.
  3. Tell the developer that they need to be a 'team player' and accept the majority's decision, after reviewing the current risk register entries.
  4. Ignore the behavior and hope the developer moves on once the spike is successful.

Sign up free to see the explanation and track your rank →

More Project Management Professional Hybrid Approaches practice

All Hybrid Approaches questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards