easy · Project Management Professional hybrid
A senior developer at Nimbus Clinics is upset because their idea for a spike was rejected by the group in favor of another. They are now being very quiet in meetings.
What should the project manager do first?
- Publicly praise the developer's idea in the next meeting to make them feel better.
- Meet with the developer privately to acknowledge their contribution and understand their feelings about the group's decision.
- Tell the developer that they need to be a 'team player' and accept the majority's decision, after reviewing the current risk register entries.
- Ignore the behavior and hope the developer moves on once the spike is successful.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?