easy · Project Management Professional Hybrid Approaches

At the Briarpoint Municipal waste-to-energy project, a hybrid initiative, the project manager realizes the high-power environmental regulator has not responded to three consecutive status reports.

What should the project manager do first?

  1. Update the communications management plan to increase the frequency of reports sent to the regulator.
  2. Escalate the regulator’s silence to the Briarpoint Municipal sponsor to ensure official pressure is applied.
  3. Schedule a private one-on-one video call with the regulator to understand their communication needs.
  4. Mark the regulator as 'Resistant' in the stakeholder engagement assessment matrix and monitor the situation.