easy · Project Management Professional hybrid

At Dovetail Clinics, a hybrid project is integrating a new scheduling system. During a daily standup for the software workstream, two senior developers argue heatedly over the database schema, delaying the meeting.

What should the project manager do first?

  1. Reassign one of the developers to a different workstream to prevent further friction.
  2. Immediately decide which schema to use to ensure the standup stays within its timebox.
  3. Meet with both developers together in a private setting to facilitate a resolution.
  4. Escalate the disagreement to the Chief Technology Officer to make a final architectural decision.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials