easy · Project Management Professional hybrid
At Dovetail Clinics, a hybrid project is integrating a new scheduling system. During a daily standup for the software workstream, two senior developers argue heatedly over the database schema, delaying the meeting.
What should the project manager do first?
- Reassign one of the developers to a different workstream to prevent further friction.
- Immediately decide which schema to use to ensure the standup stays within its timebox.
- Meet with both developers together in a private setting to facilitate a resolution.
- Escalate the disagreement to the Chief Technology Officer to make a final architectural decision.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?