KomFi. Academy

easy · Project Management Professional Hybrid Approaches

A hybrid project at Harborline Transit is being monitored. The latest S-curve shows EV < PV and EV < AC.

What should the project manager do first?

  1. Analyze the variance to see if the delay is on the critical path.
  2. Review the agile team's burn-up chart to see if they can finish early.
  3. Ask the Change Control Board for a contingency reserve release.
  4. Add more resources to the project to increase the EV.

Sign up free to see the explanation and track your rank →

More Project Management Professional Hybrid Approaches practice

All Hybrid Approaches questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards