easy · Project Management Professional hybrid
A hybrid project at Harborline Transit is being monitored. The latest S-curve shows EV < PV and EV < AC.
What should the project manager do first?
- Analyze the variance to see if the delay is on the critical path.
- Review the agile team's burn-up chart to see if they can finish early.
- Ask the Change Control Board for a contingency reserve release.
- Add more resources to the project to increase the EV.
Sign up free to see the explanation and track your rank →