On a project at Thornfield Labs, a risk that was identified and given a 'Mitigate' strategy has just occurred. The impact is higher than anticipated, and the mitigation was only partially effective.

What should the project manager do first?

  1. Transfer the risk to an insurance provider to avoid any further financial impact on the project.
  2. Submit a change request to the Change Control Board to increase the management reserve for the project.
  3. Implement the contingency plan or workaround and then evaluate the remaining residual risk.
  4. Meet with the risk owner to discuss why the original mitigation strategy failed so badly.