On a project at Thornfield Labs, a risk that was identified and given a 'Mitigate' strategy has just occurred. The impact is higher than anticipated, and the mitigation was only partially effective.
What should the project manager do first?
- Transfer the risk to an insurance provider to avoid any further financial impact on the project.
- Submit a change request to the Change Control Board to increase the management reserve for the project.
- Implement the contingency plan or workaround and then evaluate the remaining residual risk.
- Meet with the risk owner to discuss why the original mitigation strategy failed so badly.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?