easy · Project Management Professional hybrid

Ironwood Grid is using a predictive approach for a substation build. A stakeholder requests a change to the wiring specifications.

What should the project manager do first?

  1. Perform an impact analysis on the project's cost, schedule, and quality.
  2. Escalate the request to the sponsor for an immediate approval or rejection.
  3. Update the scope baseline to include the new specifications immediately.
  4. Reject the request because the scope was already finalized in the planning phase.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials