hard · Project Management Professional hybrid
Trestle Ports is using a hybrid approach to automate container tracking. The predictive workstream uses a fixed-price contract with a vendor. The project manager discovers the vendor is using unlicensed software to design the port layouts.
What should the project manager do first?
- Document the discovery and report the incident to the organization's legal and procurement departments.
- Inform the Product Owner that the port layouts may be subject to legal delays.
- Meet with the vendor to demand they purchase the licenses before the next milestone.
- Perform a risk assessment to see if the unlicensed software affects the quality of the layouts, without revisiting the agreed prioritization criteria.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?