hard · Project Management Professional hybrid

At Nimbus Clinics, a hybrid project to deploy a telemedicine platform is underway. The hardware installation in 40 clinics follows a predictive schedule, while the application's user interface is being developed in two-week sprints. At the end of month 4, the hardware workstream reports a CPI of 0.82 and an SPI of 1.05. Meanwhile, the software team's velocity has dropped from 30 points to 22 points.

What should the project manager do first?

  1. Escalate the hardware cost overrun to the project sponsor and request additional contingency funds.
  2. Submit a change request to the Change Control Board to rebaseline the software team's delivery velocity.
  3. Perform a root-cause analysis on the hardware cost variance to determine why efficiency is low.
  4. Direct the software team to increase their velocity to 30 points in the next sprint to maintain the release date.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials