hard · Project Management Professional hybrid

Quill Digital is running a hybrid project for Solstice Labs. The predictive component's performance measurement baseline (PMB) is showing a VAC of -$400,000. The adaptive component has a stable velocity of 20 points per sprint. To recover the variance, the PMO suggests the project manager cut the remaining 60 story points of adaptive work and reallocate those labor costs.

What should the project manager do first?

  1. Tell the adaptive team they must increase their velocity to 30 points per sprint to ensure the 60 points are finished before the budget is exhausted.
  2. Consult the Benefits Management Plan and the Business Case to determine the impact of the 60 points on the project's overall value delivery.
  3. Submit a change request to the CCB to reduce the application scope and rebaseline the infrastructure cost.
  4. Accept the PMO's recommendation and issue a stop-work order to the adaptive application workstream.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials