easy · Project Management Professional hybrid
A stakeholder at Driftwood Health asks a project manager to add a new reporting feature to the patient database during a routine meeting. The project is currently following a predictive baseline.
What should the project manager do next?
- Ask the developers to estimate the effort and add it to the next work package if it is small.
- Submit the request to the Change Control Board for immediate approval to keep the stakeholder happy.
- Document the request in the change log and perform an initial impact analysis.
- Refuse the request because the scope was finalized during the planning phase.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?