easy · Project Management Professional hybrid

A stakeholder at Driftwood Health asks a project manager to add a new reporting feature to the patient database during a routine meeting. The project is currently following a predictive baseline.

What should the project manager do next?

  1. Ask the developers to estimate the effort and add it to the next work package if it is small.
  2. Submit the request to the Change Control Board for immediate approval to keep the stakeholder happy.
  3. Document the request in the change log and perform an initial impact analysis.
  4. Refuse the request because the scope was finalized during the planning phase.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials