easy · Project Management Professional hybrid
At Nimbus Clinics, a senior developer is blocking the progress of a technical spike by refusing to share environment access with a peer due to a personal grievance. This is an urgent impediment.
What should the project manager do next?
- Submit a formal request to HR to initiate a disciplinary review for the senior developer.
- Wait for the next Retrospective to allow the team to discuss and resolve the access issue collectively, while documenting the decision in the issue log.
- Meet with the senior developer privately to understand the grievance and insist on professional compliance with the project's needs.
- Immediately reassign the spike to another developer to avoid further schedule delays.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?