medium · Project Management Professional hybrid
The Dovetail Clinics project manager discovers that Desire for a new system is low because staff believe it will eventually lead to headcount reductions. Awareness of the technical benefits is high.
What should the project manager do?
- Ignore the rumors and focus the team on completing the sprint backlog to ensure the technical delivery is on time.
- Conduct a cost-benefit analysis showing that the automation will save the clinic 22% in operational expenses over the next 3 years, while documenting the decision in the issue log.
- Facilitate a meeting with the executive sponsor to have them explicitly address job security and the future role of staff in the new environment.
- Offer a 'retention bonus' to all staff who successfully pass the final user acceptance testing of the new system.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?