easy · Project Management Professional hybrid
Quill Digital's CEO asks a Scrum team member to add a 'small' logo to the homepage during an active sprint. The team member is about to start the work.
What should the project manager (Scrum Master) do?
- Formally reject the request because the sprint scope is frozen.
- Allow the change because it is a small request from the highest-ranking stakeholder, while documenting the decision in the issue log.
- Shield the team from the request and redirect the CEO to the Product Owner for backlog prioritization.
- Convene a Change Control Board meeting to analyze the impact on the sprint schedule.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?