hard · Project Management Professional hybrid

A developer at Grayling Software tells the Scrum Master that a third-party API integration is blocked because the vendor has not provided the necessary credentials. The sprint ends in two days.

What should the Scrum Master do next?

  1. Contact the vendor's account manager to expedite the delivery of the credentials.
  2. Discuss the vendor's poor performance during the upcoming sprint review with stakeholders.
  3. Move the blocked story back to the product backlog and mark the sprint as successful.
  4. Ask the developer to work on a different story from the product backlog instead.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials