hard · Project Management Professional hybrid
A developer at Grayling Software tells the Scrum Master that a third-party API integration is blocked because the vendor has not provided the necessary credentials. The sprint ends in two days.
What should the Scrum Master do next?
- Contact the vendor's account manager to expedite the delivery of the credentials.
- Discuss the vendor's poor performance during the upcoming sprint review with stakeholders.
- Move the blocked story back to the product backlog and mark the sprint as successful.
- Ask the developer to work on a different story from the product backlog instead.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?