A Westfork project manager realizes that the Salience model results from initiation are no longer accurate because several council members have changed committees.

What should they do?

  1. Ask the PMO to provide a new stakeholder list for the project.
  2. Re-run the stakeholder identification and analysis process immediately.
  3. Wait for the next quarterly project review to update the register.
  4. Assume the council members' interests will remain the same despite their new roles.