medium · Project Management Professional hybrid
Westfork Municipal is using Kotter’s model to implement a new ERP system. The project manager has successfully 'Enlisted a Volunteer Army' of enthusiastic early adopters. However, several senior clerks are spreading misinformation about the system’s complexity.
Which action is most appropriate?
- Pair the enthusiastic volunteers with the resistant clerks to demonstrate the system's ease of use in a peer-to-peer setting.
- Increase the budget for the training phase to ensure all clerks have more time with the software, while documenting the decision in the issue log.
- Identify the clerks and move them to a different department that is not affected by the change.
- Issue a formal correction via the CIO’s office to debunk the misinformation publicly.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?