At Dovetail Clinics, a project to implement a digital health record is facing resistance from senior physicians who feel the system is too slow. The project manager wants to improve engagement.

Which action should be taken first?

  1. Send a weekly newsletter highlighting the benefits of the system and the successful go-live dates.
  2. Meet privately with the lead physicians to understand their specific concerns and workflows.
  3. Ask the hospital CEO to issue a mandate that all physicians must use the new system.
  4. Update the stakeholder engagement plan to categorize the physicians as 'Resistant'.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials