KomFi. Academy

medium · Project Management Professional Hybrid Approaches

At Nimbus Clinics, a data migration issue has caused a two-week delay in the predictive workstream. The project manager needs to determine the impact on the total project duration.

Which calculation is required?

  1. Calculate the project's TCPI to determine the new productivity rate required for the app team.
  2. Use Little's Law to determine the new cycle time for the infrastructure deliverables.
  3. Immediately crash the remaining infrastructure activities by adding more resources.
  4. Perform a critical path analysis to see if the migration activity has consumed its total float.

Sign up free to see the explanation and track your rank →

More Project Management Professional Hybrid Approaches practice

All Hybrid Approaches questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards