medium · Project Management Professional hybrid

At Nimbus Clinics, a data migration issue has caused a two-week delay in the predictive workstream. The project manager needs to determine the impact on the total project duration.

Which calculation is required?

  1. Calculate the project's TCPI to determine the new productivity rate required for the app team.
  2. Use Little's Law to determine the new cycle time for the infrastructure deliverables.
  3. Immediately crash the remaining infrastructure activities by adding more resources.
  4. Perform a critical path analysis to see if the migration activity has consumed its total float.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials