medium · Project Management Professional hybrid
Trestle Ports is managing a fleet of dredging vessels using a hybrid model. The project manager observes that fuel consumption is significantly higher than the planned value in the cost baseline.
Which process should the project manager use to address this physical resource variance?
- Manage Team
- Direct and Manage Project Work
- Control Resources
- Control Quality