easy · Project Management Professional hybrid

Ironwood Grid is using Expected Monetary Value (EMV) to prioritize risks. Risk 1 has a 20% probability and an impact of 100,000. Risk 2 has a 50% probability and an impact of50,000.

Which risk has the higher EMV?

  1. Risk 1
  2. They both have the same EMV.
  3. Risk 2
  4. It depends on whether the risk is a threat or an opportunity.

Sign up free to see the explanation and track your rank →

More Project Management Professional hybrid practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials