medium · Project Management Professional hybrid
A project manager at Westfork Municipal is evaluating the 'Urgency' of a change according to Kotter’s model.
Which scenario demonstrates the highest urgency?
- A state audit has threatened to withdraw city funding if the new transparency system is not live by Q3.
- The project manager believes the new system will improve staff morale significantly, while documenting the decision in the issue log.
- A competitor city has recently upgraded their tax software.
- The current system is five years old and the maintenance contract is up for renewal.
Sign up free to see the explanation and track your rank →
More Project Management Professional hybrid practice
- What should the project manager do?
- What is the Scrum Master's primary focus here as a servant leader?
- What should the project manager investigate first?
- What should the project manager do first?
- Which SECI mode is most active?
- What does 'Consulted' mean for the local Community Group in this context?
- Which Mindset Rule is the highest priority?
- Who is traditionally 'Accountable' for the effectiveness of this adaptive ceremony?