medium · Project Management Professional adaptive
Cinderwell Water uses a Kanban board to manage maintenance tasks. The team's average throughput is 5 tasks per day, and they currently have 25 tasks in progress.
According to Little's Law, what is the average cycle time for a task?
- The cycle time is 0.2 days.
- The cycle time is 125 days.
- The cycle time is 5 days.
- The cycle time is 20 days.