easy · Project Management Professional adaptive

During a Trestle Ports retrospective, several team members express frustration with the current 'Definition of Done,' leading to a tense argument.

How should the Scrum Master handle this?

  1. Remind the team that the Definition of Done is a fixed baseline and cannot be changed mid-project.
  2. Facilitate a discussion to reach a consensus on an updated Definition of Done.
  3. Wait until the next project phase to address the concerns when the team is calmer.
  4. Assign the most senior developer to rewrite the Definition of Done to resolve the dispute.

Sign up free to see the explanation and track your rank →

More Project Management Professional adaptive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials