easy · Project Management Professional adaptive
At Trestle Ports, an agile team is currently in the Storming stage. During the daily standup, two senior developers openly disagree about the refactoring approach for the harbor logistics module, causing the meeting to exceed its timebox.
What should the Scrum Master do first?
- Meet with both developers privately to understand their concerns and facilitate a resolution.
- Escalate the disagreement to the Engineering Director to make a final decision.
- Update the Team Charter to include a rule prohibiting technical debates during the daily standup.
- Instruct the developers to follow the architectural design previously outlined by the lead engineer.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?
- How should the project manager proceed to maintain the adaptive mindset?