Members of the Trestle Ports agile team have started forming cliques, leading to communication silos and uneven workloads.

How should the project manager address this Storming behavior?

  1. Facilitate a team-building exercise and review the Team Charter together.
  2. Reassign tasks specifically to force members of different cliques to work together.
  3. Wait for the Performing stage where these issues naturally disappear.
  4. Inform the cliques that their behavior is affecting the project's bottom line.