easy · Project Management Professional adaptive
At Harborline Transit, an agile team member is consistently finishing their tasks early but isn't assisting others. The Scrum Master observes the team's overall velocity (V) is stagnant.
What should the Scrum Master do next?
- Meet privately with the team member to understand their perspective on team collaboration.
- Assign the surplus tasks from the rest of the team to the faster team member.
- Report the team member's lack of cooperation to the functional manager for a formal review.
- Increase the story point estimates for the underperforming team members.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?
- How should the project manager proceed to maintain the adaptive mindset?