A project manager at Kestrel Civic is leading a team new to agile. During the first few standups, the developers are reporting their status directly to the project manager.
What is the best way for the project manager to handle this?
- Appoint a different team member to receive the reports each day to distribute the responsibility.
- Coach the team to use the standup to coordinate with each other toward the sprint goal.
- Continue receiving reports to ensure the project manager stays fully informed of progress.
- Tell the team they can skip the standup and just update the dashboard instead.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?
- How should the project manager proceed to maintain the adaptive mindset?