medium · Project Management Professional adaptive

A Grayling Software team member suggests that 'Job Size' in WSJF should include the time spent in 'Testing' and 'Documentation'. A senior dev argues it should only be 'Coding time'.

Who is correct?

  1. The senior dev; testing and documentation are 'overhead' and shouldn't affect value-based prioritization.
  2. The team member; 'Job Size' must reflect the total effort to meet the 'Definition of Done' (DoD).
  3. Neither; the Product Owner should decide which tasks to include in the size estimate.
  4. The Project Manager should decide after checking the 'Resource Management Plan'.

Sign up free to see the explanation and track your rank →

More Project Management Professional adaptive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials