medium · Project Management Professional Adaptive / Agile
A Grayling Software team member suggests that 'Job Size' in WSJF should include the time spent in 'Testing' and 'Documentation'. A senior dev argues it should only be 'Coding time'.
Who is correct?
- The senior dev; testing and documentation are 'overhead' and shouldn't affect value-based prioritization.
- The team member; 'Job Size' must reflect the total effort to meet the 'Definition of Done' (DoD).
- Neither; the Product Owner should decide which tasks to include in the size estimate.
- The Project Manager should decide after checking the 'Resource Management Plan'.
Sign up free to see the explanation and track your rank →
More Project Management Professional Adaptive / Agile practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started… How should the project manager…
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… What is the best way for the…
- During a Trestle Ports retrospective, several team members… How should the Scrum Master…
- How should the project manager proceed to maintain the adaptive mindset?
All Adaptive / Agile questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards