easy · Project Management Professional adaptive
Cinderwell Water's project has a Budget at Completion (BAC) of 100,000. Currently, the project has earned 40,000 (EV) but has spent 50,000 (AC).
Assuming the current cost performance continues, what is the Estimate at Completion (EAC)?
- 125,000
- 80,000
- 110,000
- 90,000