Whitlock Software is delivering a 'Tax Portal' for Briarpoint Municipal. The team's velocity is 25 points. A new regulatory requirement is added to the backlog, totaling 100 points.

How does this affect the project's 'release burn-up' chart?

  1. The 'Total Scope' line will shift upward by 100 points.
  2. The velocity will decrease to account for the new complexity.
  3. The project's budget will automatically increase by 4 times the iteration cost.
  4. The 'Burn-down' line will become steeper.