medium · Project Management Professional adaptive
At Harborline Transit, a Scrum team is split on a technical approach for the new signalling API. Two senior engineers recommend a complex microservices architecture, while two junior developers express concern about the learning curve.
How should the project manager proceed to maintain the adaptive mindset?
- Escalate the disagreement to the Chief Technology Officer for a definitive ruling on the organization's architectural standards.
- Facilitate a technical deep-dive session where the team evaluates both options against the sprint goal and reaches a consensus.
- Assign the junior developers to a training course immediately to mitigate the risk of a learning curve delay.
- Make the final decision based on the senior engineers' technical expertise to ensure architectural integrity.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?