Bramble Civic's CFD shows a band for 'External Approval' that is widening significantly. The team reports that the City Council's review board only meets once a month.

How should the project manager categorize this in the next status report?

  1. As a 'Risk' that has a 50% probability of delaying the project by one month.
  2. As a team performance issue, noting that the 'Definition of Ready' was not met for these items, while documenting the decision in the issue log.
  3. As an organizational impediment that is increasing cycle time and requires a governance-level resolution.
  4. As a negative schedule variance (SV) of 15% against the project's performance baseline.

Sign up free to see the explanation and track your rank →

More Project Management Professional adaptive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials