Bramble Civic's CFD shows a band for 'External Approval' that is widening significantly. The team reports that the City Council's review board only meets once a month.

How should the project manager categorize this in the next status report?

  1. As a 'Risk' that has a 50% probability of delaying the project by one month.
  2. As a team performance issue, noting that the 'Definition of Ready' was not met for these items, while documenting the decision in the issue log.
  3. As an organizational impediment that is increasing cycle time and requires a governance-level resolution.
  4. As a negative schedule variance (SV) of 15% against the project's performance baseline.