easy · Project Management Professional Adaptive / Agile
Whitlock Software's Product Vision Board includes a 'Business Goals' section. One goal is: 'Increase annual revenue by $2M'. The team argues that they cannot track this within a single sprint.
How should the project manager guide the team?
- Inform the sponsor that the team is refusing to work toward the organization's financial objectives.
- Explain that business goals are long-term objectives that the team's short-term outcomes (Key Results) should eventually support.
- Direct the team to rewrite the goal so it can be fully achieved within the current two-week iteration, after reviewing the current risk register entries.
- Remove the goal from the Vision Board to avoid demotivating the team with unachievable targets.
Sign up free to see the explanation and track your rank →
More Project Management Professional Adaptive / Agile practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started… How should the project manager…
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… What is the best way for the…
- During a Trestle Ports retrospective, several team members… How should the Scrum Master…
- Who is correct?
All Adaptive / Agile questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards