KomFi. Academy

hard · Project Management Professional Adaptive / Agile

During a project at Valeport Energy, the project manager computes an SPI of 0.88 and a CPI of 1.15.

How should the project manager interpret these results?

  1. The project is in distress and requires immediate rebaselining of all objectives.
  2. The project is behind schedule but performing efficiently regarding costs.
  3. The project is ahead of schedule and over its planned budget.
  4. The project is on track because the favorable CPI offsets the SPI.

Sign up free to see the explanation and track your rank →

More Project Management Professional Adaptive / Agile practice

All Adaptive / Agile questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards