Grayling Software is developing a mobile app. The team is using 'Story Points' for Job Size in their WSJF calculations. A new Lead Developer suggests that since she is 20% faster than the previous lead, all 'Job Size' estimates in the backlog should be reduced by 20%.
How should the Project Manager respond?
- Ask the Product Owner to recalculate the Cost of Delay to offset the reduction in Job Size.
- Update the backlog estimates immediately to ensure the WSJF scores reflect the new, higher throughput, while documenting the decision in the issue log.
- Explain that Story Points are a measure of relative effort and complexity, not absolute time, and should remain independent of individual developer speed.
- Accept the suggestion but only for the stories specifically assigned to the new Lead Developer.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?