medium · Project Management Professional Adaptive / Agile

At Grayling Software, a retrospective reveals that the team's velocity dropped because of frequent outages in a shared testing environment. The Scrum Master discovers the environment is managed by an external department that doesn't use Agile.

How should the Scrum Master drive continuous improvement?

  1. Update the project's impediment log and wait for the external department to resolve the environment stability issues.
  2. Order the team to build their own dedicated testing environment to bypass the organizational constraint.
  3. Facilitate a value stream mapping session including members from the external department to identify and remove systemic wait times.
  4. Report the external department's poor performance to the Project Management Office (PMO) during the monthly governance meeting, without revisiting the agreed prioritization criteria.

Sign up free to see the explanation and track your rank →

More Project Management Professional Adaptive / Agile practice

All Adaptive / Agile questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards