easy · Project Management Professional adaptive
A Product Owner at Thornfield Labs insists that a user story is simple and should only be 2 points, but the Developers have estimated it at 5.
How should the Scrum Master respond?
- Suggest the team meets in the middle at 3 points to satisfy both parties.
- Escalate the Product Owner's behavior to the project sponsor for resolution.
- Protect the Developers' estimate and facilitate a conversation about the technical requirements.
- Change the estimate to 2 points to maintain a positive relationship with the Product Owner, without revisiting the agreed prioritization criteria.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?