A Product Owner at Thornfield Labs insists that a user story is simple and should only be 2 points, but the Developers have estimated it at 5.

How should the Scrum Master respond?

  1. Suggest the team meets in the middle at 3 points to satisfy both parties.
  2. Escalate the Product Owner's behavior to the project sponsor for resolution.
  3. Protect the Developers' estimate and facilitate a conversation about the technical requirements.
  4. Change the estimate to 2 points to maintain a positive relationship with the Product Owner, without revisiting the agreed prioritization criteria.

Sign up free to see the explanation and track your rank →

More Project Management Professional adaptive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials