easy · Project Management Professional adaptive
During a Daily Scrum at Thornfield Labs, a developer reports they are stuck on a task because they don't know which story point value to use for a sub-task.
How should the Scrum Master respond?
- Assign a value of 1 point to the sub-task so the developer can continue working.
- Tell the developer to stop working on that task until the next refinement session, while documenting the decision in the issue log.
- Remind the developer that story points are for the whole story, and offer to facilitate a technical discussion later.
- Ask the senior developer to provide the correct estimate for the sub-task.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?