Ironvale Grid is facing a 50-point backlog growth in a fixed-date release. The PM suggests the team use 'Vertical Slicing' for the new items. Why?

  1. Vertical slicing is a schedule compression technique similar to fast-tracking.
  2. Vertical slicing allows the team to deliver smaller, usable pieces of value sooner, providing the PO with more options for descoping less critical sub-features.
  3. Vertical slicing allows the PM to assign specific layers of the architecture to different team members.
  4. Vertical slicing reduces the total story point count of the backlog by removing architectural complexity, without revisiting the agreed prioritization criteria.