Stonehaven Transit is updating its mobile ticketing app. A regulatory change (F1) was just identified. | F1: Tax Compliance | 50 | 5 | | F2: Apple Pay | 24 | 3 | | F3: Route Map | 10 | 2 | | F4: Dark Mode | 4 | 1 | What should the project manager do first?

  1. Assign F1 to the most senior developer
  2. Direct the PO to place F1 at the top of the backlog
  3. Wait for the next Retrospective to discuss F1, after reviewing the current risk register entries.
  4. Add F1 to the current sprint immediately