During a sprint at Kestrel Civic, the team identifies that a specific open-source library used for data encryption has a critical security flaw. They switch to a more secure library.
To satisfy the Business Environment domain, what must the Project Manager ensure happens?
- A change request is submitted to the legal department to update the vendor contract terms for open-source software.
- The flawed library is added to the organizational 'blacklisted software' OPA to prevent other projects from using it.
- The team's sprint backlog is updated to reflect the time spent on the library switch.
- The Project Manager personally audits all other projects at Kestrel Civic to see if they are using the same library.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?