medium · Project Management Professional adaptive
At Whitlock Software, the team’s velocity has been 28, 32, 24, and 36 over the last four sprints. They are planning a release with a remaining backlog of 180 points.
Using the average velocity, how many sprints will it take to complete the release?
- 8 sprints
- 7 sprints
- 5 sprints
- 6 sprints
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?