medium · Project Management Professional adaptive
The Osprey Bank 'Green Finance' team is using a burn-up chart to track their progress. They notice that the total scope line is rising at nearly the same rate as the completed work line.
What does this indicate?
- The team's velocity is increasing perfectly in line with stakeholder expectations.
- The team has successfully achieved a stable flow of work.
- The project is experiencing significant scope creep or continuous backlog growth.
- The project is on track to finish exactly at the originally planned date.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?