medium · Project Management Professional adaptive

The Osprey Bank 'Green Finance' team is using a burn-up chart to track their progress. They notice that the total scope line is rising at nearly the same rate as the completed work line.

What does this indicate?

  1. The team's velocity is increasing perfectly in line with stakeholder expectations.
  2. The team has successfully achieved a stable flow of work.
  3. The project is experiencing significant scope creep or continuous backlog growth.
  4. The project is on track to finish exactly at the originally planned date.

Sign up free to see the explanation and track your rank →

More Project Management Professional adaptive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials