medium · Project Management Professional adaptive

Hearthline Energy's project burn-up chart shows the 'Total Scope' line increasing steadily every sprint while the 'Completed' line remains constant.

What does this indicate to the project manager?

  1. The project is experiencing significant scope creep or uncontrolled backlog growth.
  2. The project is on track to finish exactly as planned.
  3. The team should stop all work and re-plan the entire project from scratch, after reviewing the current risk register entries.
  4. The team is underperforming and needs to increase its velocity.

Sign up free to see the explanation and track your rank →

More Project Management Professional adaptive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials