Hearthline Energy's project burn-up chart shows the 'Total Scope' line increasing steadily every sprint while the 'Completed' line remains constant.

What does this indicate to the project manager?

  1. The project is experiencing significant scope creep or uncontrolled backlog growth.
  2. The project is on track to finish exactly as planned.
  3. The team should stop all work and re-plan the entire project from scratch, after reviewing the current risk register entries.
  4. The team is underperforming and needs to increase its velocity.