medium · Project Management Professional Adaptive / Agile
Larkspur Health is implementing an adaptive delivery model for a new patient portal. During a retrospective, the developers mention they are frequently skipping unit tests to meet the sprint commitment.
What is the best action for the Scrum Master to take?
- Increase the team's velocity targets to account for the necessary testing time in future sprints.
- Extend the current sprint by three days to allow the team to complete the skipped tests.
- Report the lack of testing to the Quality Assurance manager for formal audit.
- Facilitate a discussion to reinforce the Definition of Done (DoD) as a non-negotiable quality bar.
Sign up free to see the explanation and track your rank →
More Project Management Professional Adaptive / Agile practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started… How should the project manager…
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… What is the best way for the…
- During a Trestle Ports retrospective, several team members… How should the Scrum Master…
- Who is correct?
All Adaptive / Agile questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards